GENERAL CONDITIONS

Back to Index

1. Definitions
2. Notice to Proceed
3. Contractor's Understanding
4. Intent of Drawings and Specifications
5. Drawings and Specifications
6. Shop Drawings
7. Surveys
8. Insurance
9. Permits
10. Laws To Be Observed
11. Royalties and Patents
12. Indemnity
13. Protection of Work
14. Protection of Existing Utilities
15. Public Safety and Convenience
16. Accidents
17. Assignment of Contract
18. Sub-Contracts
19. Contractor's Responsibility
20. Rights of Various Interests
21. Engineer's Responsibility and Authority
22. Inspection of Work
23. Contractor's Employees
24. Materials, Services and Facilities
25. Workmanship and Materials
26. Inspection and Testing of Materials
27. Conformity With Plans and Specifications
28. Suspension of Work
29. Owners Right to Correct Deficiencies
30. Owners Right to Terminate Contract
31. Removal of Equipment
32. Changes in the Work
33. Extra Work
34. Operations and Storage Areas
35. Schedule of Completion
36. Order of Construction
37. Extension of Contract Time
38. Use of Completed Portions
39. Protection of Property
40. Corrections of Work before Fianl Payment
41. Deductions for Uncorrected Work
42. Work in Freezing Weather
43. Cleaning Up
44. Release of Liens
45. Progress Payments
46. Measurement of Quantities
47. Final Payment
48. Guarantee
49. Safety
50. Traffic Signing Requirements
51. Discovery of Archaeological and Other Historical
52. (Or Equal) Provisions
53. North Dakota Preference
54. Special Testing Requirements
55. Changes Requested by Contractor

SPECIAL CONDITIONS

1. Liquidated Damages
2. Use of Fire Hydrants

1.  DEFINITIONS:

AContract Documents:  The Contract consists of the following documents:

    The Advertisement, Information for Bidders, The General Conditions of

    the Contract, Special Conditions of the Contract, the Specifications and

    Drawings, special specifications, the Contract, including all additions,

    deletions and modifications incorporated therein before execution of the

    Contract. 

B.  Owner is the City of Minot, North Dakota.

C. Engineer is the City Engineer of Minot, North Dakota, or his authorized representative. 

DContractor is the Contractor named in the Contract Documents. 

EProposal is the offer of a bidder to perform the work described in the Contract Documents when made out and submitted on the prescribed Proposal Form, properly signed and guaranteed. 

F. Proposal Guaranty is the cashier's check and/or Bidder's Bond accompanying the Proposal submitted by the bidder, as a guaranty that the successful bidder will enter into a Contract with the Owner for construction of the work. 

G. Contract is the agreement covering the performance of the work described in the Contract Documents including all supplemental agreements therein and all general and special provisions pertaining to the work and materials thereof. 

H. Contractor's Bond is the approved form of security furnished by the Contractor and his Surety as a guaranty of good faith on the part of the Contractor to execute the work in accordance with the terms of the Contract. 

I. Written Notice shall be considered as served when delivered in person or sent by registered mail to the Contractor at the address shown on the Contract or to the superintendent required under paragraph 23 (a) of these general conditions. 

J. Specifications shall mean the legal and procedural documents, General Conditions of the Contract, together with modifications thereof, and the Detailed Specification Requirements, with all addenda thereto. 

K. Drawings are all general and detail official drawings or reproductions of drawings pertaining to the work or to any structure connected therewith, including such working plans as may be furnished or approved by the Engineer from time to time as the work progresses. 

L. A.S.T.M. American Society for Testing Materials.

M. A.A.S.H.T.O. American Association of State Highway and Transportation Officials.

N. NDDOT  North Dakota Department of Transportation.

O. AWWA American Water Works Association.

P.    SDR Standard Dimension Ratio.

Q.    ANSI American National Standards Institute. 

R.    WW-P Federal Specification Prefix.

SNDDOT-SS North Dakota Department Of Transportation Standard   Specifications for Road and Bridge Construction, 1997 Edition.

 Back to Top

 2.  NOTICE TO PROCEED:

The mailing or delivery of a copy of the executed Contract to the Contractor or authorized agent constitutes the "Notice to Proceed".  The Contractor shall begin and shall prosecute the work regularly and uninterruptedly thereafter (unless otherwise directed in writing by the Owner) with such force as to secure the completion of the work within the time stated in the Proposal. 

 Back to Top

3.  CONTRACTOR'S UNDERSTANDING:

It is understood and agreed that the Contractor has by careful examination, satisfied himself as to the nature of the work, the conformation of the ground, the character, quality and quantity of the materials to be encountered, the character of equipment and facilities needed preliminary to and during prosecution of the work, the general and local conditions, and all other matters, which can in any way affect the work under this Contract.  No verbal agreement with any officer, agent or employee of the Owner, either before or after the execution of the Contract, shall effect or modify any of the terms or obligations herein contained. 

 Back to Top

 4.  INTENT OF DRAWINGS AND SPECIFICATIONS:

The intent of the Drawings and Specifications is that the Contractor furnish all labor and materials, equipment and transportation necessary for the proper execution of the work unless specifically noted otherwise.  The Contractor shall do all the work shown on the Drawings and described in the Specifications and all incidental work considered necessary to complete the project in a substantial and acceptable manner, and to fully complete the work, ready for use, by the Owner. 

 Back to Top

5.  DRAWINGS AND SPECIFICATIONS:

a. Copies of Drawings and Specifications Furnished:  The Engineer will furnish to the Contractor, free of charge, four (4) copies of drawings and special Specifications reasonably  necessary for execution of the work.  All additional copies will be furnished at reproduction cost.  This paragraph does not pertain to copies of Standard Specifications, the cost of which is set forth in Sec. 17 of Information for Bidders. 

b. Discrepancies in Drawings:  Any discrepancies found between the Drawings and Specifications and site conditions or any errors or omissions in the Drawings or Specifications shall be immediately reported to the Engineer, who shall promptly correct such error or omission in writing.  Any work done by the Contractor after his discovery of such discrepancies, errors or omissions shall be done at the Contractor's risk. 

cDimensions:  Figured dimensions shall govern overscaled dimensions. 

d. Drawings and Specifications at Job Site:  One complete set of all Drawings and Specifications shall be maintained at the job site and shall be available to the Engineer or his representative at all times. 

 Back to Top

 6.  SHOP DRAWINGS:

a.    The Contractor shall provide shop drawings, settings, schedules and such other drawings as may be necessary for the prosecution of the work in the shop and in the field as required by the Drawings, Specifications or Engineer's instructions. 

b.    The Contractor shall submit for approval four (4) copies of all shop drawings and descriptive data as applicable showing all features not fully detailed on the Contract Plans but essential for a complete coordinated installation. 

c.    The approval of shop drawings indicates only that the type and kind of equipment, general method of construction and/or detailing is satisfactory but shall not be construed as a complete check.  The responsibility rests on the Contractor for the proper dimensioning, detailing of connections and incorporating into the work satisfactory material and equipment meeting the requirements of the Contract Plans and Specifications. 

 Back to Top

7.  SURVEYS:

The Engineer shall establish all line and grade surveys necessary to provide cut/fill stakes at 50 foot intervals for curb and sewer projects, 100 foot intervals for wide-area grading projects.  The Contractor shall transfer these grade and lines to the actual construction.  More detailed surveying will be done at the contractor's expense.

The Contractor shall exercise proper care in the preservation of stakes set for his use by the Engineer.  If such stakes are damaged, lost or removed by the Contractor's operations, they shall be reset at his expense.

The Contractor shall protect carefully from disturbance or damage all monuments and property markers until the Engineer has witnessed or otherwise referenced their location and shall not remove them until directed. 

 Back to Top

8.  INSURANCE:

The Contractor shall not commence work under this Contract until he has obtained the insurance required under this paragraph and filed with the City Auditor necessary insurance certificates and such insurance has been approved by the Owner, nor shall the Contractor permit any sub-contractor to commence work on his sub-contract until the insurance required of the sub-contractor has been obtained and approved. 

a. Workmen's Compensation and Employer's Liability Insurance shall be secured and maintained as required by the State of North Dakota. 

b. Public Liability, Bodily Injury, and Property Damage:

Injury of one or more persons, and/or property damage:  Per accident: $1,000,000.00

c. Automobile and Truck Public Liability, Bodily Injury, and Property Damage: 

Injury of one or more persons, and/or property damage:  Per accident: $1,000,000.00

 Back to Top

9.  PERMITS:

All permits and licenses necessary for the prosecution of the work shall be secured and paid for by the Contractor.

 Back to Top

10.  LAWS TO BE OBSERVED:

The Contractor shall give all notices and comply with all Federal, State and local laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and specified.  If the Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, he shall bear all costs arising therefrom. 

 Back to Top

11.  ROYALTIES AND PATENTS:

The Contractor shall pay all royalties and license fees.  He shall defend all suits or claims for infringement of any patent rights and shall save the Owner harmless from loss on account thereof.  The Owner shall be responsible for all such loss when a particular process or the product of a particular manufacturer or manufacturers is specified, but if the Contractor has information that the process or article specified is an infringement on a patent, he shall be responsible for such loss unless he promptly gives such information to the Engineer. 

 Back to Top

12.  INDEMNITY

The Contractor shall indemnify and save harmless the Owner from and against all losses and all claims, demands, payments, suits, actions, recoveries and judgments of every nature and description brought or recovered against him by reason of any omission or act of the Contractor, his agents or employees, in the execution of the work or in the guarding of it. 

 Back to Top

13.  PROTECTION OF WORK:

The Contractor shall, at his own expense, erect and maintain adequate signs, barricades, warning lights and take all necessary precautions for the protection of the work and the safety of the public.  All barricades and obstructions shall be protected at night by signal lights which shall be kept burning from sunset to sunrise.  The Contractor will at all times until its completion and final acceptance protect his work, apparatus and material from accidental or other damage and shall make good any damages thus occurring, at his own expense.  (See Section 50 - Traffic Signing Requirements for further information.)

The name and telephone number of the Contractor shall appear on all barricades set by him. 

 Back to Top

14.  PROTECTION OF EXISTING UTILITIES:

The Contractor, prior to excavation, shall determine the location of all existing utilities within the work area and shall exercise all due caution to prevent damage thereto during all excavating or backfilling operations.  It shall be the Contractor's responsibility to locate with the aid of a City Inspector, all utility services before any construction.  Any utility damaged during construction shall be repaired by the Contractor at his own expense.  Existing manholes and gate valves shown on the drawings are to be used by the Contractor as general information only and are not to be construed, in any way, as relieving the Contractor of any responsibilities outlined in this paragraph. 

 Back to Top

15.  PUBLIC SAFETY AND CONVENIENCE:

The Contractor shall at all times so conduct his work as to insure the least possible obstruction to traffic and inconvenience to the general public and the residents in the vicinity of the work, and to insure the protection of persons and property in a manner satisfactory to the City Engineer.  No road or street shall be closed to the public except with the permission of the City Engineer.  Fire hydrants  on or adjacent to the work shall be kept accessible to the fire-fighting equipment at all times.  Temporary provisions shall be made by the Contractor to insure the use of sidewalks and the proper functioning of all gutters, storm sewer inlets, and drainage ditches, which shall not be obstructed except as approved by the City Engineer. 

Back to Top

16.  ACCIDENTS:

The contractor shall provide, at the site, such equipment and medical facilities as are necessary to supply first-aid service to anyone who may be injured in connection with the work. 

The Contractor must promptly report in writing to the Engineer all accidents whatsoever arising out of, or in connection with, the performance of the work; which caused death, personal injury, or property damages, giving full details and statements of witnesses.  In addition, if death or serious injuries or serious damages are caused, the accident shall be reported immediately by telephone or messenger to the Engineer and the Owner. 

Back to Top

17.  ASSIGNMENT OF CONTRACT:

The Contractor shall not sublet, sell, transfer, assign or otherwise dispose of the Contract or any portion thereof, or of his right, title or interest therein, or his obligation thereunder, without written consent of the Owner. 

Back to Top

18.  SUB-CONTRACTS:

At the time specified by the Engineer the Contractor shall submit in writing to the Owner for approval of the Engineer the names of any sub-contractors proposed for the work.  Sub-contractors may not be changed except at the request or with the approval of the Engineer. The Contractor shall remain responsible to the Owner for the acts and omissions of his sub-contractors.  The Contract Documents shall not be construed as creating any contractual relation between any sub-contractor and the Owner.  The Contractor shall bind every sub-contractor by the terms of the Contract Documents. 

 Back to Top

19.  CONTRACTOR'S RESPONSIBILITY:

The Contractor shall have charge of and be responsible for the entire work under this Contract until the completion, and any imperfect or unfaithful work which may be discovered any time before the final acceptance of the work embraced in this Contract shall be corrected immediately upon request of the Owner or Engineer.  The contractor shall maintain a work force on site each workday, except during inclement weather, during the contract period until the project is completed.  Any work days not worked will be taken into account on any Request for Extension of Time for Completion and/or assessment of liquidated damages. 

 Back to Top

20.  RIGHTS OF VARIOUS INTERESTS:

Wherever work being done by the Owner's employees or by other contractors is contiguous to work covered by this Contract, the respective rights of the various interests involved shall be established by the Engineer, to secure the completion of the various portions of the work in general harmony. 

 Back to Top

21.  ENGINEER'S RESPONSIBILITY AND AUTHORITY:

The Engineer will require, on the Owner's behalf, that the construction be performed by the Contractor in accordance with the plans and specifications.  The Engineer shall also have authority on behalf of the Owner to require the proper prosecution of the installation of the work to the extent that the forces of labor may be increased or decreased by his order to insure the execution of the Contract in the time and manner prescribed.      The Engineer, shall, within a reasonable time after presentation, make decisions in writing on any claims between the Contractor and Owner, such decisions shall be regarded as final. 

 Back to Top

22.  INSPECTION OF WORK:

a.    Inspectors may be stationed on the work to report to the Engineer as to the progress of the work, the manner in which it is being performed, and also to report whenever it appears that materials furnished and work performed by the Contractor fail to fulfill the requirements of the specifications and Contract.  The Inspector may direct the attention of the Contractor to such failure or infringement but such inspection shall not relieve the Contractor from any obligations to furnish acceptable materials or to provide completed construction that is satisfactory in every particular. 

b.    In case of any dispute arising between the Inspector and the Contractor as to material furnished or the manner of performing the work, the Inspector shall have the authority to reject materials, and/or suspend the work until the questions and issue can be referred to and decided by the Engineer.  Inspectors are not authorized to revoke, alter, enlarge, relay, or release any requirements of these specifications, nor to issue instructions contrary to the plans and specifications.  Inspectors shall in no case act as management of the work by the Contractor. 

c.    See special section 53 on page 28 for testing requirements for work not inspected by the Engineer. 

Back to Top

23.  CONTRACTOR'S EMPLOYEES:

a.    Contractor's Superintendent:  A qualified superintendent, who is acceptable to the Engineer, shall be maintained on the work and give efficient supervision to the work until its completion.  The superintendent shall have full authority to act in behalf of the Contractor, and all directions given to the superintendent shall be considered given to the Contractor.  The Contractor shall remove from the project any superintendent unsatisfactory to the Engineer.

b    Character of Workmen:  Any foreman or workman employed by the Contractor, who in the opinion of the Engineer, does not perform his work in a skillful manner, or appears to be incompetent or incorrigible shall be dismissed by the Contractor or his representatives when requested by the Engineer, and such persons shall not again be permitted to return to the work without the written consent of the Engineer. 

 Back to Top

24.  MATERIALS, SERVICES AND FACILITIES:

It is understood that, except as otherwise specifically stated in the Contract Documents, the Contractor shall provide and pay for all materials, labor, mechanics for labor, tools, equipment, equipment rental, water, light, power, transportation, superintendent, temporary construction of every nature whatsoever necessary to execute complete and deliver the work within the specified time. 

 Back to Top

25.  WORKMANSHIP AND MATERIALS:

All work done and all material and equipment furnished by the Contractor shall strictly conform to the plans and specifications.  Competent labor, mechanics, and tradesmen shall be used on all work. 

The acceptance at any time of the materials by or in behalf of the Owner shall not be a bar to future rejection if they are subsequently found to be defective or inferior in quality or uniformity of the material specified. 

Whenever any material shall be condemned by the Engineer such material shall be removed at once from the line of work at the Contractor's expense, and shall not be brought back. 

 Back to Top

26.  INSPECTION AND TESTING OF MATERIALS:

a.    During the progress of the work, it shall be subject to the inspection of the Engineer, and the Contractor shall afford every reasonable facility and assistance to the Engineer to make such inspection thorough and intelligent. 

b.    The fact that the Engineer is at the job site shall not be taken as an acceptance of the Contractor's work or any part of it.  The Contractor shall notify the Engineer upon completion of his Contract and the work shall be given final inspection and test by the Engineer and if all parts of the work are acceptable and comply with the intent of the plans and specifications, a recommendation of final acceptance will be made by the Engineer to the Owner. 

c.    Contractor shall submit to the Engineer from time to time, or when called upon to do so, and without charge, samples or specifications of materials he proposes to use. 

d.    For projects under the control of the City of Minot, the City shall call and pay for all materials testing, including locally supplied materials and on site tests such as density tests for soil and asphalt paving.  Exceptions to this general condition shall include material certifications and tests provided by non-local suppliers, job mix formulas required for paving mixes and perform- ance tests of certain materials in place such as watermain and sewermain pressure tests.  Any re-tests required due to test failures shall be paid for by the contractor.  The testing laboratory will be selected by the Engineer and all tests shall be in accordance with the standards of the ASTM, AASHTO, and other recognized standards.

 Back to Top

27.  CONFORMITY WITH PLANS AND SPECIFICATIONS:

All materials which do not conform to requirements of the Contract Documents, are not equal to samples approved by the Engineer, or are in any way unsatisfactory or unsuited to the purpose for which they are intended, shall be rejected.  Any defective work whether the result of poor workmanship, use of defective materials, damage through carelessness or any other cause shall be removed within ten (10) days after written notice is given by the Engineer, and the work shall be re-executed by the Contractor.  The fact that the Engineer may have previously overlooked such defective work shall not constitute an acceptance of any part of it. 

In the event the Engineer finds the materials furnished, work performed, or the finished product not in conformity with the plans and/or specifications but that the portion of the work affected will, in his opinion, result in a finished product having a level of safety, economy, durability, and workmanship acceptable to the owner, he will advise the owner (Minot City Council) of his determination that the affected work be accepted and remain in place.  In this event, the engineer will document his determination and recommend to the owner a basis of acceptance which will provide for an adjustment in the contract price for the affected portion of the work.  The engineer's determination and recommended contract price adjustments will be based on good engineering judgement and such tests or retests of the affected work as are, in his opinion, needed.  The acceptance by the owner of the engineer's recommendation with respect to the adjustment in the contract price shall constitute final determination of said adjustment.  Thereafter, the changes in contract price shall be covered by contract modifications (change order or supplemental agreement) as applicable. 

 Back to Top

28.  SUSPENSION OF WORK:

The Engineer shall have the authority to suspend the work, wholly or in part, for such period or periods, as he may deem necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for prosecution of the work, or failure on the part of the contractor to carry out the provisions of the Contract or to supply materials meeting the requirements of the specifications.  The Contractor shall not suspend operation without the Engineer's permission. 

 Back to Top

29.  OWNER'S RIGHT TO CORRECT DEFICIENCIES:

If the Contractor shall neglect to prosecute the work properly or fail to perform any provision of this Contract, the Owner, after three (3) days written notice to the Contractor may, without prejudice to any other remedy he may have, correct such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor. 

Back to Top

30.  OWNER'S RIGHT TO TERMINATE CONTRACT:

The Owner shall have the right to terminate the employment of the Contractor after giving seven (7) days written notice of termination to the Contractor in the event of any default by the Contractor and upon receiving written notice from the Engineer certifying cause for such action.  In the event of such termination the Owner may take possession of the work and of all materials, tools, and equipment thereon and may finish the work by whatever method and means he may select.  In such a case, the Contractor shall not be entitled to receive any further payment until the work is finished.  If the unpaid balance of the Contract price shall exceed the expense of finishing the work, including compensation for additional managerial and administrative services, such excess shall be paid to the Contractor.  If such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner. 

 

It shall be considered default by the Contractor whenever he shall:

a    Undergo voluntary or involuntary bankruptcy, become insolvent, or assign his assets for the benefit of his creditor. 

b.    Disregard or violate important provisions of the Contract Documents or Engineer's instructions, or fail to prosecute the work according to the agreed schedule of completion, including extensions thereof. 

c.    Fail to provide a qualified superintendent, competent workmen or subcontractor, or proper materials, or fail to make prompt payment therefor. 

 Back to Top

31.  REMOVAL OF EQUIPMENT:

At the termination of this Contract, or in the case of annulment of the Contract before completion, the Contractor, if notified to do so by the Owner, shall  promptly remove any part or all of his equipment and supplies from the property of the Owner.  Should the Contractor fail to remove such equipment and supplies the Owner shall have the right to remove them at the Contractor's expense. 

 Back to Top

32.  CHANGES IN THE WORK:

The Owner may, as the need arises, order changes in the work through additions, deletions, or modifications without invalidating the Contract.  Compensation and time of completion affected by the change shall be adjusted at the time of ordering such change.  The value of such change shall be determined by unit prices named in the Contract. 

 Back to Top

33.  EXTRA WORK:

33.1 Written Change Order
33.2  Force Account Work

33.2.1  Labor

33.2.2 Bond, Insurance, and Taxes
33.2.3 Materials

33.2.4 Equipment

33.2.5 Miscellaneous

33.2.6  Subcontracting

33.2.7 Authority of Engineer

33.2.8 Daily Records

33.2.9 Statements

33.2.10  Compensation

33.2.11.  Specialty Work

33.3 Formal Audit

Back to Top

If any work should be required for which no unit price for the supplying of material or the performance of such work is provided in the proposal, it shall be classified as "Extra Work".  However, it is specifically understood that if no bid items for the removal and replacement of paving, concrete, sod or any other ground surface improvements are included in the proposal, all such items disturbed shall be removed, and replaced in original condition or better as non-pay items.

33.1  Written Change Order  For any extra work required, the engineer for the owner and the contractor shall first attempt to negotiate a price by written change order.  Consulting engineers hired by the Owner for any projects covered by these Standard Specifications shall be required to obtain approvals for any extra work as set forth hereinafter.  The engineer shall determine any and all quantities of materials necessary to accomplish the extra work.  The contractor shall provide to the engineer written quotes from suppliers for the price of the materials, an estimate of manhours needed to perform the work together with wage and employee benefits information, and an estimate of hours for equipment to be used with rates to be charged for such equipment.  The contractor will be allowed to add 15% to the total cost of the previous items.  The engineer and contractor shall then negotiate a change order price and the written change order shall be prepared by the engineer.  If the price negotiated and agreed upon exceeds $10,000 or 10% of the original contract amount, whichever is greater, the change order must be approved by the City Engineer and the City Manager, and the City Manager shall notify the City Council regarding the change order within 24 hours of its approval.  No extra work covered by any change order shall be done by

the contractor without a valid change order.  However, the contractor may be allowed to proceed with extra work without formal change order approval if, in the opinion of the engineer, the immediate commencement of the extra work will relieve a situation of hazard, or substantial inconvenience, to the public.  A change order (or force account agreement) shall be prepared thereafter.

Back to Extra Work Index

33.2  Force Account Work  If the owner and the contractor cannot agree to a price for extra work pursuant to the methods set forth hereinbefore, the extra work shall be done by force account.  However, the final amount paid for extra work by force account shall not exceed the lowest price offered by the contractor in the change order process.  Extra work by force account shall not proceed without written approval from the City Engineer and the City Manager of the City of Minot.  Extra work done by force account shall be handled and compensated in the following manner. 

Back to Extra Work Index

33.2.1  Labor.  For all laborers and supervisors in the direct charge of the specific operations, the Contractor will receive the wage paid for each hour the laborers and the supervisor are actually engaged in the Force Account work, but not to exceed any rate of wage agreed to before beginning the work. 

A.  The Contractor will receive actual costs paid to or on behalf of the workers for subsistence and travel allowance, health and welfare benefits, pension fund, or other fringe benefits when such amounts are required by collective bargaining agreement or employment contract generally applicable to the classes of labor employed in work, but excepting any amounts already included in wage rates paid.  Any subsistence or travel allowance paid to workers shall be prorated according to the number of hours employed on the Force Account and other classes of work. 

B.  The Contractor will be paid an amount equal to 15% of the sum of the above items for overhead and profit. 

Back to Extra Work Index

33.2.2 Bond, Insurance, and Taxes.  For premiums paid on additional bond, property damage, liability, workmen's compensation, and unemployment insurance, and for social security taxes on the Force Account wages, the Contractor will receive the actual cost, to which the sum of 6% will be added. The Contractor shall furnish satisfactory evidence of the premium rates. 

Back to Extra Work Index

33.2.3 Materials.  For all materials accepted by the Engineer and permanently installed into the work, the Contractor will receive the actual cost (including transportation charges paid by the Contractor) of the material delivered, to which a sum equal to 15% will be added.  For materials used in connection with (but not entered permanently into) the work, a reasonable depreciation will be allowed. 

Back to Extra Work Index

33.2.4 Equipment.  If the engineer and Contractor cannot agree on equipment rates for force account work, the following method of determining equipment rates shall be used.  For use of authorized equipment and additional traffic control devices required by the Force Account work, the Contractor will receive rental rates determined according to the then current issue of the North Dakota Department of Transportation publication entitled "Rental Rates for Equipment and Traffic Control Devices."  This manual shall constitute a part of this Specification.  No percentage will be added to these rates. 

Procedures governing rented or owner-operated equipment, attachments and accessories, types and quantity of equipment, measurement of equipment time, use of equipment in excess of 50 hours per week, stand-by time, and equipment transportation charges will be as set forth in the NDDOT publication "Rental Rates for Equipment and Traffic Control Devices."

Back to Extra Work Index

33.2.5 Miscellaneous.  No additional allowance will be made for use of small tools not listed in the rental rate schedule or other costs for which no specific allowance has been provided. 

Back to Extra Work Index

33.2.6  Subcontracting.  For any Force Account or Extra Work performed by a Subcontractor with the written authorization of the Engineer, the Contractor will receive an additional allowance for administrative and overhead expense.  The additional allowance will be a percentage of the total Force Account or Extra Work invoice equal to 10%.

Back to Extra Work Index

33.2.7 Authority of Engineer.  The Engineer has authority to require alterations in equipment and labor force assigned to Force Account work.  The Engineer is also authorized to limit overtime work to that normally used on the project for work of similar nature, or to require overtime when an emergency exists, and to require the stopping of Force Account work when adverse conditions severely limit productivity. 

Back to Extra Work Index

33.2.8 Daily Records.  Each day the Contractor's representative and the Engineer shall compare and reconcile the records of labor, materials, and equipment used in the Force Account work. 

Back to Extra Work Index

33.2.9 Statements.  The Contractor shall furnish the Engineer with duplicate itemized statements of the cost for the Force Account work, detailed as follows:

A.  Payroll for laborers and foreman. 

B.  Quantities of materials, prices, extensions, and transportation costs paid by the Contractor. 

Statements shall be accompanied by receipted invoices for materials used, including transportation charges by the Contractor.  The statements shall be adjusted when applicable to reflect any discounts offered by the supplier.  If materials used in the Force Account work are not specifically purchased but are taken from the Contractor's stock, the Contractor shall furnish an affidavit certifying that such materials were taken from stock, that the quantity claimed was actually used, and that the price and transportation costs claimed are the Contractor's actual costs.  After receipt of statements and invoices, the Engineer will prepare a summary statement of the Force Account work which will be submitted to the Contractor for verification and signature.  The value of the Force Account work covered by approved statements will be included in progressive pay estimates. 

Back to Extra Work Index

33.2.10  Compensation.  Compensation provided by previous provisions of this Section shall be accepted by the Contractor as payment in full for "Extra Work" performed on a Force Account basis. 

Back to Extra Work Index

33.2.11.  Specialty Work.  When the Engineer and Contractor determine a special service or item of work cannot be performed by the Contractor or authorized Subcontractors, the service or Extra Work item may be performed by a specialist.  Invoices for such work on the basis of current market price may be accepted without complete itemization of labor, material, and equipment cost when it is not practicable and not according to established practice of the special service industry to provide such complete itemization.  To compensate the Contractor for administrative and overhead costs, an allowance will be added to the specialty work invoice equal to 10%.

Back to Extra Work Index

33.3 Formal Audit. The owner, has the right to audit the contractor's records with respect to extra work done by change order or force account.

Back to Extra Work Index
Back to Top

34.  OPERATIONS AND STORAGE AREAS:

All operations of the Contractor, including storage of materials, shall be confined to areas authorized by the Owner.  Any additional land and access thereto not shown on the drawings that may be required for temporary construction facilities or for storage of materials shall be provided by the Contractor with no liability to the Owner. 

Back to Top

35.  SCHEDULE OF COMPLETION:

The Contractor shall submit at such times as may reasonably be requested by the Engineer, schedules which shall show the order in which the Contractor proposes to carry on the work, with dates at which the Contractor will start the several parts of the work and estimated dates of completion of the several parts.  The contract may specify that certain segments of the contract must be completed before other segments are commenced by the contractor.  In this case, interim completion dates may be applied and liquidated damages enforced on segments not completed as required. 

 Back to Top

36.  ORDER OF CONSTRUCTION:

The Engineer shall have control of the order in which the various parts of the construction work are to be performed.  The order of work as determined by the Contractor will be followed except where the Engineer determines that such order would not be to the best interest of the Owner or the general public. 

 Back to Top

37.  EXTENSION OF CONTRACT TIME:

A delay beyond the Contractor's control occasioned by an Act of God, or Act or omission on the part of the Owner or by strikes, lockouts, fire, etc., may entitle the Contractor to an extension of time in which to complete the work as determined by the Engineer; provided, however, that the Contractor shall immediately give written notice to the Engineer of the cause of such delay.  Delay in material shipping shall not be sufficient reason for an extension unless so determined by the Engineer.  The granting of any extension of time shall not be the basis for any claim for extra costs incurred by the Contractor. 

 Back to Top

38.  USE OF COMPLETED PORTIONS:

The Owner shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding that the time for completing the entire work of such portions may not have expired; but such taking shall not relieve the Contractor of his responsibility to complete the project in accordance with the Contract Documents.  If such prior use increases the cost of or delays the completion of uncompleted work or causes refinishing of completed work, the Contractor shall be entitled to such extra compensation, or extension of time or both, as the Engineer may determine. 

 Back to Top

39.  PROTECTION OF PROPERTY:

The Contractor shall, at his own expense, protect by falsework, braces, shoring or other effective means, all buildings, walls, fences, and other property along his line of work or affected directly by his work, against all damage and shall repair or repay the injured owners for such damage. 

Back to Top 

40.  CORRECTIONS OF WORK BEFORE FINAL PAYMENT:

     The Contractor shall promptly remove from the premises all materials condemned by the Engineer as failing to conform to the Contract, whether incorporated in the work or not, and the Contractor shall promptly replace and re-execute his own work in accordance with the Contract and without expense to the Owner and shall bear the expense of making good all work of the Contractor destroyed or damaged by such removal or replacement.

Back to Top 

41.  DEDUCTION FOR UNCORRECTED WORK:

If the Engineer deems it inexpedient to correct work injured or not in accordance with the Contract, an equitable deduction from the contract price shall be made therefore.

Back to Top 

 42.  WORK IN FREEZING WEATHER:

Work may not continue in freezing weather, unless specifically authorized in writing by the Engineer.

Back to Top 

 43.  CLEANING UP:

The Contractor must keep all streets, alleys and sidewalks as free from material and debris as the character of the work will permit, and upon completion of any part of the work, must within reasonable time, remove all surplus material and debris, and leave right-of-way in acceptable conditions.   

Failure to comply with this provision after due and proper notice has been given by the Owner, will be sufficient grounds for the Owner to proceed to clean up such material and debris and make such repairs, charging same to the Contractor, who hereby agrees to the provisions as above set forth.

Back to Top 

 44.  RELEASE OF LIENS:

If required, the Contractor shall deliver to the Owner a complete release of all liens arising out of this Contract before the retained percentage or before the final payment is paid.  If any lien remains unsatisfied after all payments are made, the Contractor shall refund to the Owner such amounts as the Owner may have been compelled to pay in discharging such liens including all costs and a reasonable attorney's fee.

Back to Top 

 45.  PROGRESS PAYMENTS:

So long as the work herein contracted for is carried on in accordance with the provisions of the Contract, the Engineer will, on or before the first day of each month, make an approximate estimate of the value of the work performed during the previous month.  Progress payments in the amount of 90% of the estimate will be made to the Contractor in cash within approximately thirty (30) days after preparation of the partial estimate by the Engineer and approval of same by the Owner.  The Owner may at all times reserve and retain out of said payment all sums it may be authorized to reserve or retain.   

The amount retained will be reduced to 5% after completion of 50% of the project and to 1% after substantial completion of the project if the Engineer finds that progress is satisfactory and that final completion will not be jeopardized by such reduction. 

For each progress payment, an additional $1000 shall be retained by the City until it has been determined by the State Commissioner of Labor that no action or fines are pending against the contractor under the provisions of NDCC 43-07-20.

Back to Top

46.  MEASUREMENT OF QUANTITIES:

The quantities of work performed will be computed by the Engineer on the basis of measurements taken by the Engineer, or authorized representative, and these measurements shall be final and binding.   

All work computed under the Contract shall be measured by the Engineer according to the United States Standard Measurements and Weights.  Measurements for the various items will be made as provided in the specifications.

Back to Top 

 47.  FINAL PAYMENT: 

The Engineer will, as soon as practicable after the completion and final acceptance of the work, make a final estimate of the amount of work done under the Contract.  This estimate shall be based on "As Built" measurements made by the Engineer, and based on unit prices in the proposal plus all approved additions less all approved deductions and less previous payments made. 

Back to Top

 48.  GUARANTEE:

The Contractor guarantees all work constructed under the Contract for a period of one (l) year from the date of final acceptance, against defects in material or workmanship.  He shall bear the entire cost and expense of all repairs which may, from any imperfection in work or materials become necessary within that time. 

If at any time within the period of guarantee, any of the work included in the guarantee shall, in the judgement of the Engineer, require any repair or reconstruction, he shall notify the Contractor to make the repairs required.  Upon receipt of the notice, the Contractor shall proceed with such repairs and shall complete the same within a reasonable time. 

If the Contractor shall neglect or fail to proceed with the repairs within twenty (20) days or if, in the opinion of the Engineer, the repairs do not admit of sufficient delay to issue said notice and to await the action of the Contractor, then the Owner shall have the right to cause such repairs to be made and the cost shall be paid by the Contractor.  The liability of the bond given to secure the faithful performance of the Contract shall continue during the full guarantee period. 

At the expiration of the guarantee period, the Contractor and his surety shall be released from further obligation under this Contract, providing the Engineer will certify to the Owner that the work performed under this Contract is in good and proper condition at the time. 

Back to Top

 49.  SAFETY:

The Contractor and Sub-contractors shall perform the work in compliance with the latest North Dakota Safety Code adopted by the North Dakota Workmen's Compensation Bureau.

Safety apparel meeting the AVSI/ISEA 107-1999 Standard for High-Visibility Safety Apparel shall be worn when working in the right-of-way. 

Back to Top

 50.  TRAFFIC SIGNING REQUIREMENTS:

The contractor shall provide for all required traffic control devices as shown on the "Traffic Control Plan" included with the plans.  All equipment and devices must be in place before any work commences in the area effected by the Traffic Control Plan.  If no Traffic Control Plan is included with the plans, the contractor shall prepare and submit a traffic control plan to the Engineer at least one week prior to commencement of work.  The City of Minot Traffic Division may be available to the contractor to determine signing requirements.  However, any assistance provided by the Traffic Division shall in no way relieve the contractor of his responsibility to provide proper traffic control pursuant to the Manual on Uniform Traffic Control Devices, part VI, U.S. Department of Transportation, Federal Highway Administration, 1988, as revised.

Existing signs of any type that interfere with construction shall be removed and replaced in the same location by the Contractor, at no cost to the owner, unless otherwise noted. 

Back to Top

51.  DISCOVERY OF ARCHAEOLOGICAL AND OTHER HISTORICAL ITEMS: 

In the event of an archaeological find during any phase of construction, the following procedure will be followed. 

A. Construction shall be halted, with as little disruption to the archaeological site as possible. 

B. The Contractor shall notify the Owner, who shall contact the State Historic Preservation Officer. 

C. The State Historic Preservation Officer may decide to have an archaeologist inspect the site and make recommendations about the steps needed to protect the site, before construction is resumed. 

D. Any claim made by the contractor for down time or additional work required by the State Historic Preservation Officer shall be classified as extra work.  See Section 33 Extra Work. 

E.  Should any artifacts, housing sites, etc., be uncovered, the same procedure shall be followed as outlined for an archaeological find.

Back to Top 

 52.  (OR EQUAL) PROVISIONS:

The following procedure shall be followed to determine the equivalency of any material that is not directly referred to in these specifications:   

A. The Contractor shall submit a sample of the proposed product, with all the available literature, to the Engineer. 

B. The Engineer will determine equivalency of the proposed product. 

C. The decision of the Engineer as to equivalency of the proposed product shall be final. 

Any variation in the design concept of the proposed product, as compared to listed products, shall be grounds for rejection.

Availability of parts, cost of parts, and work involved in replacing said parts, can also be used by the Engineer in making his decision as to equivalency.

Back to Top 

53.  North Dakota Preference:

Unless prohibited by federal law or regulation, and except for those projects being funded by federal aid funds, the contractor must give preference to the employment of bona fide North Dakota residents, with preference given first to honorably discharged disabled veterans and veterans of the armed forces of the United States, who are deemed to be qualified in the performance of the work to be performed by the contractor.  (See NDCC Chapter 43-07 for further requirements).

Back to Top

54.  SPECIAL TESTING REQUIREMENTS:

On all projects not under direct supervision of the Minot City Engineering Department the following tests must be made by an independent qualified person or agency and certified copies of results must be submitted to the City Engineer.  Any areas not conforming to specifications must be repaired or replaced without cost to the City of Minot.  Tests are to be paid for by the Owner, Contractor, or Engineer for the project.  Failed tests shall be paid for by the contractor. 

TYPE OF WORK               FREQUENCY OF TEST               TYPE OF TEST

(PUBLIC UTILITIES)

Water Mains                 Valve to valve                    Pressure 

Sewer Mains                 Each MH Length             Alignment & infiltration

Water Services               Each Service                     Pressure

Sewer Service                Each Service                 Slope & Jointing

Sewer & Water Main

Trenches                      4 Per Block              Compaction @ 12" and @ 60"

Sewer & Water Trenches    30% of Units Per Block       Compaction @ 12" and @ 60"

Paving Preparation         2 Per Block (not over trenches)            Compaction @ 12" 

(PRIVATE UTILITIES)  including all power, telephone, gas, and Cable T.V. main lines and services and private portions of water & sewer services within public Right Of Way. 

Main Line Trenches             2 Per Block                  Compaction @ 18"

Service Trenches              1 Each Trench                 Compaction @ 18"

Repair Trenches               1 Each Trench                 Compaction @ 18"

Concrete                       One per day         Air Content, Slump,Compression(3 Cyl)

Asphalt                        Two per day                      Samples

Subgrade                      Each 1500 yd2                    Compaction

Road Base                     Each 1500 yd2                    Compaction

At the option of the City Engineer, the tests required of private utilities for service trenches, repair trenches and main line trenches may be waived if the utility company supplies a letter of agreement to warranty all work against trench settlement for a period of 5 years after completion.  Tests shall be required however, for main line trenches over 50 feet in length which cut through existing paved areas.

Back to Top 

 55.  Changes Requested by Contractor:

The contractor may request changes to the plans or specifications which may result in a finished product equal to or better than the project as contracted.  Any such requests shall be in writing and either submitted for review at the preconstruction conference or at least two (2) weeks prior to the work affected by the proposed change or changes.  The City Engineer shall make the final determination on requested changes in writing. 

Back to Top

S P E C I A L   C O N D I T I O N S

1.  A. LIQUIDATED DAMAGES:

Should the Contractor fail to complete the work, including items requiring correction, at the time specified in the proposal, or within such extensions of time as may be allowed in writing by the City Engineer, the Contractor shall pay to the City of Minot as and for liquidated damages for such failure of completion a sum of money based upon the value of such contract in accordance with the following schedule: 

ORIGINAL CONTRACT              AMOUNT LIQUIDATED DAMAGES  

Over - To & Including                      Calendar Day        Working Day

$      0  - $ 25,000                                $   40                        $   60

  25,000  -   50,000                                   60                             90

  50,000  -  100,000                               100                           125

 100,000  -  500,000                              140                           170

 Over $500,000                                      180                           220

For clarification, calendar day means days not worked and calendar day is not added coincidentally with working day.

The Contractor understands that the following clause is part of the construction contract whether it does or does not appear in said contract.

The time limit for the completion of the work herein provided for is of the essence of this contract, and in case Contractor shall fail to complete the work hereunder, within the time aforesaid, or within such extensions of time, as may be allowed by the City Engineer, he agrees to pay the City $      (this blank will be filled in with the appropriate daily figure from the above schedule) dollars for each and every day the time consumed in said performance and completion exceeds the time hereinbefore allowed for that purpose, which said sum, in view of the difficulty in ascertaining the loss which City will suffer by reason of delay in the performance of the work hereunder is hereby agreed upon, fixed and determined by the parties hereto as liquidated damages that City will suffer by reason of said delay and default, and not as a penalty; and City shall and may deduct and retain the amount of such liquidated damages out of the money which may be due or become due under this contract.

Back to Top

    B.  LIQUIDATED DAMAGES FOR CURB, GUTTER AND SIDEWALK CONTRACT:

In the yearly Curb, Gutter and Sidewalk contract, the contractor is given a specific amount of work to complete each month.  If the contractor fails to complete such work in the time allowed, the liquidated damages set forth in the above table shall be invoked.

Back to Top

2.  USE OF FIRE HYDRANTS AND VALVES:

No person or contractor shall operate any water system valve without permission from the Superintendent of Water and Sewers. 

The Contractor is requested to make special note of the following paragraphs taken from the City Ordinances:

31-44.  No person except City Employees in performance of their official duties shall open or cause to be opened any fire hydrant without written permission of the Superintendent of Water and Sewers.   

1-8.  The doing of any act prohibited or declared to be unlawful by this Code, or the omission or failure to perform any act or duty required by this Code, is, unless another penalty is specified, punishable by a fine in a sum not exceeding five hundred dollars ($500.00) and imprisonment not to exceed thirty (30) days, or by both such fine and imprisonment.  Each day any person violates any provision of this Code shall constitute a separate offense.

It shall be the responsibility of the Contractor to secure permission from the Superintendent of Water and Sewers at least 24 hours before any hydrant is used.  Such permission will be given by the Superintendent only after he has determined that the usage will not be a detriment to the water system or to Fire Department operations.

 Back to Top